Permits and documentation for demolition
A building cannot simply be taken down. Here is what the building authority usually wants, who prepares it and in what order it has to happen.
Permit for removing a structure
The framework is set by Czech Building Act No. 283/2021 Coll. A permit from the building authority is usually needed for a structure that itself required a permit, and for a structure containing asbestos. Small structures follow a simpler regime. The exact scope differs by building and by authority, so we check it with the building authority the plot falls under rather than guessing from the internet.
An application for a permit to remove a structure usually contains:
- The expected start and end dates of the demolition works.
- The way the demolition works will be carried out.
- Identification of neighbouring plots and buildings if the demolition needs them or affects them.
- Information on whether the structure contains asbestos or asbestos can be expected.
- The documentation for removal of the structure.
- Binding opinions, statements and decisions of the authorities concerned, where they are required for the particular building.
What the authority may set in the permit
- A deadline by which the structure has to be removed.
- The procedure and method of the demolition works.
- Conditions for complying with technical regulations and protecting public interests.
- How the plot is to be treated after the structure is removed.
- An obligation to notify who the building contractor is or who exercises construction supervision.
- An obligation to report reaching a given stage of the works for an inspection.
These are conditions, not formalities. The way the plot has to be left and the deadline for removal in particular can make a job dearer when they are discovered at the moment of signing.
The demolition design and who prepares it
The documentation for removal of a structure is usually prepared by a qualified designer, not by the demolition company. It describes the building, the demolition procedure, how the surroundings are secured and how the waste is handled. The scope differs with what is being demolished: a shed is a different job from a cellared house in a terrace.
The order matters more than it seems. You look for a designer before a demolition company, because without the documentation the application cannot be filed, and without a permit no demolition date can be agreed. A company that promises you a date before you know whether you have a permit is promising something it does not control.
| Step | Whose turn it is | What you end up holding |
|---|---|---|
| Documentation for removal of the structure | Qualified designer (usually) | The basis without which the application cannot be filed |
| Application for a removal permit | The owner | A permit with conditions and a deadline |
| Disconnecting the utilities | The owner, with each network operator separately | Confirmation of disconnection of electricity, gas, water and sewerage |
| Notifying asbestos works | An authorised company | A separate quote and a disposal document for hazardous waste |
| Transfer of waste to an authorised entity | The demolition company | Weighbridge tickets and a waste transfer document |
Frequently asked questions about permits
When is no removal permit required?
Some small structures follow a simpler regime. What decides it is whether the structure itself required a permit and whether it contains asbestos. Because the interpretation differs from authority to authority, we recommend checking with the particular building authority. We will do that for you.
Can the demolition permit be part of the permit for a new building?
If you apply at the same time for removal of a structure and for a permit for a project on the same site, the decision on removal can form part of the decision permitting the project. It sounds like a detail, but it saves one round of proceedings.
What if the structure contains asbestos?
A structure with asbestos needs a permit and cannot be removed under the simplified route. Work with asbestos is notified in advance to the regional public health authority and carried out by a company with the relevant authorisation. We do not do this part ourselves; we handle it separately with an authorised company.
Related pages
Tell us what needs to come down
The address, a few photos and one sentence about what has to go is enough. We go through the enquiry and pass it to a demolition company that works in your area. If we have no partner there, we say so straight away instead of leaving you waiting.
- Photos from outside and inside say more than a description. A phone camera is fine.
- Tell us whether machinery can reach the building, or whether it has to come down by hand.
- If you suspect asbestos (corrugated cement sheets, old pipe lagging), say so right away.