Why demolition is priced per cubic metre and how to work the volume out
When you ask for an indicative demolition price and the other side asks about square metres, the two of you are talking about different things. Demolition is priced in cubic metres, that is by the volume of structure that has to go. The reason is simple: the work, the machinery and the waste all grow with volume, not with footprint.
Two houses, the same footprint, twice the difference
A single-storey house with a loft and timber floors and no cellar has a considerably smaller volume than a cellared house with concrete floors and a high ground floor on the same built-up area. The difference in volume then shows up in machine hours and in the number of skips hauled away, and that is exactly what makes the price.
How to estimate the volume yourself
- Measure the external dimensions of the building at ground level. That is the built-up area.
- Measure or estimate the height from the cellar floor (or the foundation base) to the ridge or the parapet.
- Multiply. For a house with a pitched roof, count the loft at roughly half its height.
- Count the whole cellar. People forget it and it is often tens of percent of the volume.
The result will not be exact and is not meant to be. It is there so that you compare two quotes on the same job and notice when someone is working with a different volume than the competition.
What volume does not tell you
Volume is only one axis. The second is material: reinforced concrete with dense rebar is demolished and disposed of differently from brick. The third is access: a house at the end of a narrow lane comes down with smaller machines and takes longer. The fourth is what has to remain on the plot. That is why the price is confirmed after a site visit even when you know the volume precisely.
Why it is sometimes priced by the tonne
Disposal at a landfill is usually paid for by weight rather than volume, so both units appear side by side in quotes. Clean brick rubble is heavy and a skip is usually full by weight before it is full by volume. When you see a price per tonne in a quote, ask whether it is for sorted rubble or for a mix.
The rest of the inputs that make up the price are set out on what drives the price of demolition.